Power and Water Corporation
Date: 25 December 2025
Report: Power Water - Sewerage overflows - wet weather overflows at multiple locations PDF (846.2 KB)
  • Sewage pumping station (SPS042) – Nemarluk Drive, Ludmilla
    • 1. Discharge point: 12.4144849 ºS, 130.8503154 ºE
    • 2. Final point: 12.4144254 ºS, 130.8458232 ºE
  • Sewage pumping station (SP008) – Lakeside Dr, Alawa
    • 1. Discharge point: 12.3806488 ºS, 130.8656252 ºE
    • 2. Final point: 12.3805596 ºS, 130.8665271 ºE
  • Sewage pumping station (SP035) – Vesty’s Beach
    • 1. Discharge point: 12.4305953 °S, 130.8355978 °E
    • 2. Final point: 12.4315167 °S, 130.8362544 °E
Alice Springs Town Council - Regional Waste Management Facility
Date: 23 December 2025
Report: Fire on Landfill and Demolition Cell PDF (183.4 KB)
80 Commonage Road, Ilparpa NT 0870
Power and Water Corporation
Date: 22-25 November 2025
Report:  Discharge of sewage effluent from sewage network in multiple locations (Cyclone Fina) PDF (3.3 MB)
Multiple locations – Darwin, Darwin northern suburbs, East Arm, Northcrest, Freds Pass, Humpty Doo
GEMCO Mining Pty Ltd
Date: 18 November 2025
Report:  Stormwater release PDF (268.5 KB)
GEMCO Port Facility.
IOR Pty Ltd
Date: 16 November 2025
Report:  Diesel spill PDF (929.1 KB)
Stuart Hwy &, Bohning Rd, Alice Springs NT 0870. Exact location: -23.835129, 133.835937.
Clough BMD Joint Venture (CBJV)
Date: 3 November 2025
Report: Hydraulic oil/Transmission fluid leak from Project site. PDF (127.7 KB)
Lot Information: 865 Berrimah Road, East Arm NT 0822
INPEX
Date: 12 October 2025
Report: Heating medium oil spill at Ichthys LNG facility  PDF (224.4 KB)
144 Wickham Point Road (INPEX Ichthys LNG facility)
Norsta Maritime Pty Ltd
Date: 3 October 2025
Report: Oil leak from HMAS Cape Schanck at HMAS Coonawarra Wharf Fremantle Basin PDF (31.9 KB)
HMAS Coonawarra Wharf Precinct, Larrakeyah, NT 0820
Power and Water Corporation
Date: 19 September 2025
Report: Discharge of raw sewage effluent from sewerage network PDF (1.4 MB)
Lakeside Dr SPS (SP008): Discharge Point: 130.8684868, -12.3812859 Final Discharge Point: 130.8678589, -12.3811767
Power and Water Corporation
Date: 10 September 2025
Report: Discharge of sewage effluent from sewage network in Winnellie PDF (251.6 KB)

Lot 6495 Town of Darwin (73 Reichardt St Winnellie NT 0820)

VTG Waste and Recycling Pty Ltd
Date: 03 September 2025
Report: Oil Spill 4/32 Bishop Street, Woolner PDF (141.9 KB)

Lot 5458, Town of Darwin (4/32 Bsihop Street Woolner, NT 0820)

Frances Bay Marine Facility
Date: 05 August 2025
Report: Oil leak from vessel Skye at Fisherman's Wharf PDF (75.3 KB)

Fisherman’s Wharf
Frances Bay Drive, Darwin City, NT 0800
Darwin Port
Date: 26 July 2025
Report: Oily bilge water spill at East Arm Wharf PDF (31.3 KB)
East Arm Wharf
880 Berrimah Rd, East Arm, NT 0822
Litchfield Council
Date: 23 July 2025
Report: Fire on Humpty Doo Waste Transfer Station PDF (29.7 KB)
Humpty Doo Waste Transfer Station
Litchfield Council
Date: 17 July 2025
Report: Grass fire Howard Springs PDF (25.4 KB)
Howard Springs Waste Transfer Station

Roper Gulf Regional Council
Date: 14 July 2025
Report: Tyre fire at Bulman landfill PDF (33.7 KB)

Approximately 1 km south of Bulman

NT Portion 1646, Central Arnhem Rd, West Arnhem

Power and Water Corporation
Date: 14 July 2025
Report: Diesel Spill - Elcho Island Galiwinku  PDF (1012.0 KB)
Discharge Point: 135.5725514 E, -12.0311178 S
Final Discharge Point: Immediately surrounding the discharge point
Litchfield Council
Date: 9 July 2025
Report: Fire at Howard Springs Waste Transfer Station PDF (145.6 KB)
Howard Springs Waste Transfer Station
City of Darwin
Date: 30 June 2025
Report: Fire on Stage 6 commercial and demolition waste disposal area PDF (151.0 KB)
Lot 3952 Vanderlin Drive, Karama
Power and Water Corporation
Date: 30 June 2025
Report: Discharge of sewage effluent from sewer rising main break in Yulara PDF (346.4 KB)
Yulara Drive, Lot 254, Town of Yulara
Power and Water Corporation
Date: 8 June 2025
Report: Spill of sewage - Ross Highway, Alice Springs PDF (209.4 KB)

Latitude: -23.7375855723997,

Longitude: 133.8694636639

Power and Water Corporation
Date: 2 June 2025
Report: Discharge of diluted sewage effluent from Bicentennial Rd sewage pumping station PDF (249.0 KB)

79 Bicentennial Rd, Katherine South (Lot 2357).

Bicentennial sewage pumping station (SP409):
Discharge Point: -14.4672595S, 132.2779853E
Final Discharge Point: -14.4669696S, 132.2765799E

Power and Water Corporation
Date: 30 May 2025
Report: Discharge of diluted and fully treated sewage effluent from the Finke wastewater treatment ponds PDF (844.4 KB)

NT Portion 3819, Ghan

Latitude: -25.563937

Longitude: 134.572893

Power and Water Corporation
Date: 16 May 2025
Report: Diesel Spill - SnakeBay barge landing Milikapiti – Melville Island PDF (1.2 MB)
Discharge Point: 11.4137136 S, 130.6678966 E
Final Discharge Point: immediately surrounding source of leak
Power and Water Corporation
Date: 12 May 2025
Report: Sewer overflow - Ramingining SPS 1 PDF (524.9 KB)
Sewage overflow from Sewer Pump Station (SPS) 1 Ramingining:

Discharge Point: -12.3268236, 134.9342029 (SPS overflow main)
Final Discharge Point: -12.3269628, 134.9340617 (open area adjacent to SPS 1)
Power and Water Corporation
Date: 7 May 2025
Report: Sewer overflow - Galiwinku SPS1 PDF (281.5 KB)
Discharge Point: -12.0228731O S, 135.5631197O E
Final discharge point: -12.0227911O S, 135.5622428O E
Power and Water Corporation
Date: 4 May 2025
Report: Sewage leak from Sewer Rising Main (SRM) Galiwinku – Close Out PRL13048 PDF (479.0 KB)
Discharge Point: 12 1.9976767 S, 135 35.0084293 E (SRM Leak)

Final discharge point: 12 2.0224382 S, 135 34.9694683 E (Bushland adjacent to SRM)

Clift Freight Service
Date: 13 April 2025 at approximately 10.30 pm
Report: Diesel spill of approximately 2,500 L PDF (136.1 KB)
Erldunda Desert Oaks Resort - Soil investigation and Stockpile Assessment June 2025 PDF (6.9 MB)
Erldunda Desert Oaks Resort (corner Lassetter and Stuart Highways, Ghan, NT 0872
-25.197806, 133.199982

NTEX Pty Ltd
Date : 11 April 2025
Report:  Hydraulic Oil Spill in yard  PDF (260.2 KB)

NTEX, 29 Muramats Road, East Arm 0828

City of Darwin
Date: 10 April 2025
Report: Leachate seepage from Stage 3 PDF (170.8 KB)

Lot 3952 Vanderlin Drive, Karama

Power and Water Corporation
Date : 8 April 2025
Report:  Sewer Overflow - Galiwinku SPS1 PDF (275.9 KB)

Galiwinku SPS 1:
Discharge Point: -12.0228731O S, 135.5631197O E
Final Discharge Point: -12.0227911O S, 135.5622428O E

Power and Water Corporation
Date: 2 April 2025
Report: Discharge of highly diluted sewage effluent from sewerage network at Ludmilla and Lakeside Drive Sewage Pump Stations PDF (825.6 KB)

Discharge point:
Ludmilla SPS (SP042):
Discharge Point: 130.8503163E, -12.4144833S
Final Discharge Point: 130.8458232E, -12.4144254S

Lakeside Dr SPS (SP008):
Discharge Point: 130.8656139E, -12.3806369S
Final Discharge Point: 130.8665271E, -12.3805596S

Power and Water Corporation
Date: 2 April 2025
Report: Discharge of sewage from sewerage network PDF (323.8 KB)
Discharge Point: 130.8556279E, 12.4207879S
(approx. location of inspection opening)
Final Discharge Point: 130.8552604E, 12.4206388S (stormwater drain)
Power and Water Corporation
Date: 29 March 2025
Report: Sewer Overflow - Pine Creek SPS PDF (323.5 KB)

Discharge Point: 131.8392783 E, 13.8164929 S (emergency discharge pipe outlet)
Final discharge point: 131.8386789 E, 13.8140982 S (Copperfield Creek)

Power and Water Corporation
Date: 28 March 2025
Report: Sewer Overflow - Wet weather overflows at multiple locations in Darwin PDF (684.8 KB)

Overflow relief point on cnr Rapid Creek/Trower Rds:

  • Discharge Point: -12.385673 S, 130.864963 E
  • Final Discharge Point: -12.385733 S, 130.865954 E

Overflow relief point at 24 East Point Rd:

  • Discharge Point: -12.434417 S, 130.8379474 E
  • Final Discharge Point: -12.4336630 S, 130.8358461 E (Vestey’s Lagoon)

Two access chambers on cnr Gregory St/East Point Rd:

  • Discharge Point: -12.4320022 S, 130.8378083 E and -12.4321384 S, 130.8379457 E
  • Final Discharge Point: 12.4316500 S, 130.8362400 E
Power and Water Corporation
Date: 20 March 2025
Report: Sewer Overflow - Ludmilla and Lakeside Dr SPS PDF (834.4 KB)

Ludmilla sewage pumping station (SP042):

  • Discharge Point: 130.8503163E, -12.4144833S
  • Final Discharge Point: 130.8458232E, -12.4144254S

Lakeside Dr sewage pumping station (SP008):

  • Discharge Point: 130.8656139E, -12.3806369S
  • Final Discharge Point: 130.8665271E, -12.3805596S
Power and Water Corporation
Date: 7 March 2025
Report: Sewage spill from sewage infrastructure in Lajamanu PDF (954.2 KB)
Lot 317 Lajamanu
  1. Discharge Point 1: 130.6382723E, 18.3355463S
  2. Final Discharge Point 1: 130.6386727E, 18.3355875S
  3. Final Discharge Point 2: 130.6375135E, 18.3354169S
Power and Water Corporation
Date: 1 March 2025 at 13:45am.
Report: Discharge of sewage from sewerage network – Manhole Cover PDF (294.4 KB)
LOT340 Townsite of Ngukurr
  1. Discharge Point: 134.7344436E, 14.7312560S (manhole)
  2. Final Discharge Point: 134.7347793E, 14.7308923S (bushland)
Power and Water Corporation
Date: 27 February 2025 at 11:58am.
Report: Discharge of sewage - Yulara Sewage Pump Station PDF (401.4 KB)
61 Coolibah Close, Yulara
  1. Discharge Point: 130.9932448E, 25.2446830S
  2. Final Discharge Point: 130.9932448E, 25.2446830S
Power and Water Corporation
Date: 18 February 2025 at 4pm. Discharge ceased at 12:45am.
Report: Treated Sewage Effluent Spill Minyerri, NT PDF (350.3 KB)
Discharge Point: 134.0692884, -15.2242136
Final discharge point: 134.0682557, -15.2240387
Power and Water Corporation
Date: 13 February 2025
Report: Wet weather effluent spills multiple locations PDF (1.2 MB)
Sewer overflow relief point:
24 East Point Road, Parap
  1. Discharge Point: 12.4342520 S, 130.8376568 E
  2. Final discharge point: 12.4336630 S, 130.8358461 E (Vestey’s Lagoon)
Corner of Trower Road and Rapid Creek Road, Rapid Creek
  1. Discharge Point: 12.385673 S, 130.864963 E
  2. Final Point: 12.385733 S, 130.865954 E
Corner Casuarina Drive & Palm St, Nightcliff
  1. Discharge Point: 12.3834339 S, 130.8432689 E
  2. Final Point: 12.3839750 S, 130.8429805 E
Manhole: Corner of East Point Road and Gregory Street, Parap
  1. Discharge Point: 12.4320025 S, 130.8378102 E
  2. Discharge Point: 12.4321381 S, 130.8379435 E
  3. Final Point: 12.4320215 S, 130.8362208 E
Power and Water Corporation
Date: 31 January 2025
Report: Power and Water Sewage Spill - Fairway Waters SPS PDF (390.1 KB)
Fairway waters (LOT 11025, Town of Palmerston)
Final Discharge Point: 130.9715498 E, -12.4723699 S
McArthur River Mining Pty Ltd
Date: 30 January 2025
Report: 1kg concentrate spill on Carpentaria Hwy PDF (864.5 KB)

E: 644025.20 N: 8257280.83
MGA Zone 53 (GDA94)

McArthur River Mining Pty Ltd
Date: 27 January 2025
Report: 5 tonnes concentrate spill on 22km from Bing Bong Loading Facility PDF (1.3 MB)
E: 644002 N: 8257249
MGA Zone 53 (GDA94)
Power and Water Corporation
Date: 22 January 2025
Report:  Discharge of sewage - Yulara Sewage Pump Station PDF (1.8 MB)

Lot 262 Town of Yulara
130.9840019E, 25.2355906S

Power and Water Corporation
Date: 21 January 2025
Report: Adelaide River Ponds - Sewer Effleunt Spill PDF (230.4 KB)

Adelaide River Wastewater Ponds (Lot 169)

  1. Discharge Point: 131.1059588, -13.2302731
  2. Final discharge point: 131.1029843, -13.2273207
Power and Water Corporation
Date: 18 January 2025
Report:  Discharge of sewage from sewerage network - Manhole cover PDF (1.3 MB)

Lot 151 Miyamurda Street, Umbakumba
136.8118906E, 13.8573439S

McArthur River Mining Pty Ltd
Date: 12 January 2025
Report: Concentrate spil in Carpentaria Highway PDF (1.6 MB)
631946E, 8218930N
645042E, 8264798N
645066E, 8265086N
638589E, 8229772N
642160E, 8239861N
MGA Zone 53 (GDA94) coordinate reference system
McArthur River Mining Pty Ltd
Date: 12 January 2025
Report: Concentrate spill that occurred on Carpentaria Hwy PDF (950.9 KB)
631946E, 8218930N
645042E, 8264798N
645066E, 8265086N
MGA Zone 53 (GDA94) coordinate reference system
Power and Water Corporation
Date: 11 January 2025
Report: Discharge of sewage effluent from sewage infrastructure - Alice Springs PDF (2.2 MB)
LOT 10766, LOT 5807
2 Ulpaya Road, Stuart, NT 0870
Power and Water Corporation
Date: 8 January 2025
Report: Ludmilla Sewage Pumping Station Discharge PDF (2.9 MB)